Opened 10-06-2026 by aonif, last activity 3mo ago

  1. Incoming0 days10-06-2026
  2. Declined0.1 days10-06-2026
  3. Needs Champion0.3 days10-06-2026
  4. In Review0 days10-06-2026
  5. Needs Champion0 days10-06-2026
  6. In Review4.6 days10-06-2026
  7. Ready for Vote9.1 days15-06-2026
  8. Voting Live0 days24-06-2026
  9. Approvedsince 24-06-2026
Funding request
393,000 CC
Champion named in file
\[Required: SIG or Tech & Ops Committee sponsor\]
Discussion
9 messages
4 people

Development Fund Proposal Submission

Proposal file: /proposals/2026-06-FCS-splice-sv-ui-ux-improvements.md


Summary

This proposal clears 18 open issues from the SV governance UI backlog in canton-network/splice, delivering a complete shared component library, polished governance pages and operator-facing functionality improvements. The work reduces the maintenance burden on the Splice core team, improves the daily experience of every SV operator on the network and demonstrates that the Development Fund can drive upstream code quality through external contribution.


Checklist

  • Proposal file added under /proposals/
  • Milestones and funding amounts defined
  • Acceptance criteria included
  • Alignment with Canton priorities described

Notes for Reviewers

The 18 in-scope issues were recommended and selected through the Splice contributor channel, so the scope is already aligned with the Splice maintainers. Estimates are based on Digital Asset's own day-level estimates as a reference, validated and confirmed by FCS's engineering team. Timeframes include a one-week maintainer review and acceptance allowance per milestone, following guidance from the Splice maintainer DA team that milestones should reflect work that is reviewed and accepted, not only submitted.

Milestones 3

  1. SV UI Shared Component Library
  2. SV UI Layout and Page Design
  3. SV UI Governance Functionality