Proposal: PagFinance Fiat Connector for Canton

Opened 21-09-2026 by straucoinlast activity 1mo ago

  1. Incoming0 days21-09-2026
  2. Declinedsince 21-09-2026
Funding request
6,200,000 CC
Champion named in file
Needs Champion
Duration
6 months for Milestones 1 to 4, plus a performance-based adoption bounty (Milestone 5) running up to 12 months after Milestone 4
Organization
PagFinance
RFP or roadmap area
Financial Markets, Standards & Verification, RFP 13 (Payments and DeFi)
Discussion
0 messages
0 people

Development Fund Proposal Submission

Proposal file:
proposals/2026-09-PagFinance-fiat-connector.md

Applicant

Organization: PagFinance

Author / Primary Contact: Andre Straube, Founder & CEO, PagFinance

Champion: Needs Champion


Proposal Classification

Proposal Type:

  • RFP-aligned proposal
  • Individual initiative

RFP / Roadmap Area:
Financial Markets, Standards & Verification, RFP 13 (Payments and DeFi)

Label: financial-workflows-composability


Funding & Timeline

Total Funding Request:
6,200,000 CC

Project Duration:
6 months for Milestones 1 to 4, plus a performance-based adoption bounty (Milestone 5) running up to 12 months after Milestone 4

Maximum Amount: N/A

Maximum Duration: N/A


Summary

Canton has no reusable reference for connecting on-ledger token settlement to a genuinely off-ledger bank rail in either direction. Every team wanting a fiat corridor backed by an actual rail, rather than a tokenized proxy for one, starts from zero.

This proposal delivers an open-source, rail-agnostic fiat connector built on CIP-0056: Daml escrow templates, an off-ledger connector with a documented rail-adapter interface, and an integration blueprint, all Apache-2.0. It is proven on the first BRL corridor on the network, settled over PIX, running both off-ramp and on-ramp.

The ecosystem value is a repeatable bidirectional pattern any participant can fork for MXN over SPEI, USD over ACH, or EUR over SEPA by writing only a rail adapter, plus Canton's first connection to a market of 180 million PIX users.


Submission Checklist

  • Full proposal file is included in this PR
  • Organization and primary contact identified
  • Champion identified or Needs Champion selected
  • RFP / roadmap alignment identified, if applicable
  • Total funding request provided
  • Project duration provided
  • Proposal is within any RFP maximum amount
  • Proposal is within any RFP maximum duration
  • Milestones and milestone funding are defined in the proposal
  • Acceptance criteria are based on ecosystem value
  • Architectural alignment is addressed

Milestones 7

  1. CIP-0056 rail-agnostic core, off-ramp and on-ramp, on DevNet7 weeks from start
  2. Open connector and integration blueprint6 weeks after Milestone 1
  3. External security audit
  4. Audit engagement signed1 week after Milestone 2
  5. Audit report published and findings remediated4 weeks after Milestone 3.1
  6. Live BRL corridor on MainNet and public enablement8 weeks after Milestone 3.2
  7. Institutional adoption bountyup to 12 months after Milestone 4