Incoming#934 Pull requestEquilibrium (equilibrium.co)RFP 1: Enable frictionless party hosting

Proposal: Party Offboarding, offline ACS cleanup for departed parties

Opened 26-10-2026 by zvolin, last activity today

  1. Incoming0.2 days so far26-10-2026
  2. Needs Championnot reached
  3. In Reviewnot reached
  4. Ready for Votenot reached
  5. Voting Livenot reached
  6. Approvednot reached
Waiting on
Nobody has picked it up
idle 0.2 days
Funding request
Up to 1,330,000 CC base across four milestones (580,000 CC engineering, 750,000 CC adoption priced per event); renewable maintenance at 60,000 CC per quarter, accepted separately and outside the base
Champion named in file
Heslin Kim, Zenith (@heslin-zenith)
Duration
~2.5 months engineering (hard deadline at ~month 3); adoption window open for 9 months from Milestone 3 acceptance
Organization
Equilibrium (equilibrium.co)
RFP or roadmap area
RFP 1: Enable frictionless party hosting

Development Fund Proposal Submission

Proposal file: rfps/protocol-infrastructure-scalability-resilience/2026-10-Equilibrium-party-offboarding.md

Applicant

Organization: Equilibrium

Author / Primary Contact: Olli Tiainen (olli@equilibrium.co)

Champion: Heslin Kim, Zenith (@heslin-zenith)


Proposal Classification

Proposal Type:

  • RFP-aligned proposal
  • Individual initiative

RFP / Roadmap Area: RFP 1: Enable frictionless party hosting (Protocol, Infrastructure, Scalability & Resilience)

Label: party-portability-data-resilience


Funding & Timeline

Total Funding Request: Up to 1,330,000 CC base across four milestones: 580,000 CC engineering and 750,000 CC adoption priced per event. Maintenance is priced separately at 60,000 CC per quarter, accepted separately and outside the base.

Project Duration: ~2.5 months engineering (hard deadline at ~month 3); adoption window open for 9 months from Milestone 3 acceptance.

Maximum Amount: N/A. No maximum amount is stated for RFP 1 in the published roadmap.

Maximum Duration: N/A. No maximum duration is stated for RFP 1 in the published roadmap.


Summary

When a party unhosts from a participant, its active contracts stay behind in that participant's Active Contract Store: the party can no longer act on them, and the participant can never prune them. Worse, re-onboarding that party later, or any party that shared a contract with it, can fail on ACS divergence. canton-offboard lets a node operator preview those stranded copies, deactivate them safely in a maintenance window, and optionally prune them, all captured in a receipt the node can re-verify. It closes the cleanup step that Digital Asset's Party Mobility and the Decentralization Manager both leave out, so co-validation and multi-hosting rotations finish clean.


Submission Checklist

  • Full proposal file is included in this PR
  • Organization and primary contact identified
  • Champion identified or Needs Champion selected
  • RFP / roadmap alignment identified, if applicable
  • Total funding request provided
  • Project duration provided
  • Proposal is within any RFP maximum amount
  • Proposal is within any RFP maximum duration
  • Milestones and milestone funding are defined in the proposal
  • Acceptance criteria are based on ecosystem value
  • Architectural alignment is addressed

Milestones 4

  1. Read path (230,000 CC)week 4. Hard deadline: week 5. Effort: ~20 person-days.
  2. Mutate path (175,000 CC)week 7. Hard deadline: week 9. Effort: ~15 person-days.
  3. Proof path (175,000 CC)week 10. Hard deadline: week 13. Effort: ~15 person-days.
  4. Independent operator adoption (750,000 CC)